Risk assessment of public-private partnership projects for electric vehicle charging through an extended MCDM method with interval-type 2 fuzzy sets

Document Type : Research Paper

Authors
Department of Industrial Engineering, Faculty of Engineering, Shahed University, Tehran, Iran
Abstract
Due to the growing global attention to clean energy in the world, projects of electric vehicles (EVs) have greatly increased all around the world. The lack of charging infrastructure in developing countries has become a major problem. In this situation, governments engage the private sector to improve the charging infrastructure. Assessing the risk factors (RFs) under these circumstances is essential. In this paper, the important RFs are detected. Moreover, the weights of important RFs are identified through an extended version of the BWM approach. Furthermore, the overall risk levels of public-private partnership (PPP) charging projects are specified by using an integrated ELECTRE-VIKOR approach. To address uncertainty in risk identification, weighting, and ranking in practical situations, interval type-2 fuzzy sets (IT2FSs) are employed. IT2FSs provide more space for experts to cope with the uncertainty. Extended weighting and ranking methods are developed under IT2FSs. Finally, an example in the field of EV charging projects (EVCPs) is provided. The proposed framework was further validated through a comparative analysis with fuzzy VIKOR, fuzzy ELECTRE, and BWM–TOPSIS. The results demonstrated high consistency across the methods, supporting the credibility of the proposed approach.
Keywords

Ahıskalı, A., Akkan, T., & Bas, E. (2025). Evaluation of a New Approach in Water Quality Assessments Using the Modified VIKOR Method: A. Ahiskali et al. Environmental Modeling & Assessment, 30, 613-623.
Ahmadpour, M., Aghajan Nashtaei, R., & Khodadadi, M. (2025). A Model For Assessing the Financial Risk of Companies Using The Hybrid FUZZY-BWM Method. Journal of Investment Knowledge, 15, 525-556.
Alves, J. L., & Pereira, M. A. (2025). Enhancing clinical and non-clinical risk management: A case study using ELECTRE Tri-nC. Health Care Management Science, 28(4), 824-841.
Amoozad Mahdiraji, H., Arzaghi, S., Stauskis, G., & Zavadskas, E. K. (2018). A hybrid fuzzy BWM-COPRAS method for analyzing key factors of sustainable architecture. Sustainability, 10, 1626.
Asan, U. M. U. T., Soyer, A., & Bozdag, E. (2016). An Interval Type-2 Fuzzy Prioritization Approach to Project Risk Assessment. J. Multiple Valued Log. Soft Comput., 26, 541-577.
Awodi, N. J., Liu, Y. K., Ayo-Imoru, R. M., & Ayodeji, A. (2023). Fuzzy TOPSIS-based risk assessment model for effective nuclear decommissioning risk management. Progress in nuclear energy, 155, 104524.
Barzegari, M. J., & Mousavi, S. M. (2026). Mining Project Portfolio Selection Based on an Interval Type-2 Fuzzy Entropy-MARCOS Method under Uncertainty. Journal of Quality Engineering and Production Optimization, e5111.
Budayan, C., Dikmen, I., Talat Birgonul, M., & Ghaziani, A. (2018). A computerized method for delay risk assessment based on fuzzy set theory using MS Project™. KSCE Journal of Civil Engineering, 22, 2714-2725.
Cevik Onar, S., Oztaysi, B., & Kahraman, C. (2014). Strategic decision selection using hesitant fuzzy TOPSIS and interval type-2 fuzzy AHP: a case study. International Journal of Computational intelligence systems, 7, 1002-1021.
Chen, S. M., & Lee, L. W. (2010). Fuzzy multiple attributes group decision-making based on the interval type-2 TOPSIS method. Expert systems with applications, 37, 2790-2798.
Cusanno, A., Seidi, M., Yaghoubi, S., Garcia-Romeu, M. L., & Piccininni, A. (2026). Multi-criteria quality assessment of parts produced by single point incremental forming process: application of the ELECTRE method. The International Journal of Advanced Manufacturing Technology, 142, 1505-1523.
Debnath, J., & Biswas, A. (2017, July). Assessment of occupational risks in construction sites using interval type-2 fuzzy analytic hierarchy process. In Industry Interactive Innovations in Science, Engineering and Technology: Proceedings of the International Conference, I3SET 2016 (pp. 283-297). Singapore: Springer Singapore.
DeCorla-Souza, P., & Hossain, M. (2025). New Tool to Screen Financial Viability of Alternative Public–Private Partnership Structures for Delivery of Electric Vehicle-Charging Infrastructure. World Electric Vehicle Journal, 16, 30.
Demirel, H. C. (2022). Dealing with uncertainty in infrastructure public-private partnership projects (Doctoral dissertation, Delft University of Technology).
Dorfeshan, Y., Mousavi, S. M., & Vahdani, B. (2018). A multi-criteria analysis model under an interval type-2 fuzzy environment with an application to production project decision problems. Journal of Quality Engineering and Production Optimization, 3(1), 43-66.
Fattahi, R., & Khalilzadeh, M. (2018). Risk evaluation using a novel hybrid method based on FMEA, extended MULTIMOORA, and AHP methods under fuzzy environment. Safety science, 102, 290-300.
Fei, L., Liu, X., & Zhang, C. (2024). An evidential linguistic ELECTRE method for selection of emergency shelter sites. Artificial Intelligence Review, 57, 81.
Fernández, E., Figueira, J. R., Navarro, J., Solares, E., & Díaz, R. (2025). Integrating second-order effects in ELECTRE methods with an interval-based approach. Omega, 137, 103353.
Govindan, K., & Jepsen, M. B. (2016). Supplier risk assessment based on trapezoidal intuitionistic fuzzy numbers and ELECTRE TRI-C: a case illustration involving service suppliers. Journal of the Operational Research Society, 67, 339-376.
Gupta, H. (2018). Assessing organizations performance on the basis of GHRM practices using BWM and Fuzzy TOPSIS. Journal of environmental management, 226, 201-216.
Hakam, D. F., & Wasesa, M. (2025). Advancing towards Indonesia's net zero emission goals: An in-depth multi-criteria decision making (MCDM) analysis of ship-loader operations in maritime transportation using interval type-2 fuzzy AHP and TOPSIS methods. Energy Reports, 14, 552-565.
Jahangirzadeh, A., Mousavi, S. M., & Dorfeshan, Y. (2020). An extended grey relational analysis based on COPRAS method for sustainable supplier selection in project procurement problems. Journal of Quality Engineering and Production Optimization, 5(1), 103-118.
Kan, Z., Wei, Y., Zhao, T., & Cao, J. (2024). Risk evaluation of submarine pipelines in FMEA by combination of gray relation projection and VIKOR method. Ocean Engineering, 302, 117695.
Kaya, T., & Kahraman, C. (2011). An integrated fuzzy AHP–ELECTRE methodology for environmental impact assessment. Expert Systems with Applications, 38, 8553-8562.
Khan, R. U., Yin, J., Mustafa, F. S., & Wang, S. (2024). Seaport hazardous cargo loading and unloading risk assessment using interval type-2 fuzzy sets and Bayesian networks. ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering, 10, 04023065.
Kokangül, A., Polat, U., & Dağsuyu, C. (2017). A new approximation for risk assessment using the AHP and Fine Kinney methodologies. Safety science, 91, 24-32.
Li, J., Wang, J. Q., & Hu, J. H. (2019). Multi-criteria decision-making method based on dominance degree and BWM with probabilistic hesitant fuzzy information. International journal of machine learning and cybernetics, 10, 1671-1685.
Li, T., Wu, W., Li, X., Li, Y., Gong, X., et al. (2025). A Hybrid Approach Combining Scenario Deduction and Type-2 Fuzzy Set-Based Bayesian Network for Failure Risk Assessment in Solar Tower Power Plants. Sustainability, 17, 4774.
Liu, J., & Wei, Q. (2018). Risk evaluation of electric vehicle charging infrastructure public-private partnership projects in China using fuzzy TOPSIS. Journal of cleaner production, 189, 211-222.
Liu, Y., Wang, Y., Guo, A., & Ding, N. (2025). Risk assessment in anti-money laundering: an integrated entropy-AHP-VIKOR model. Risk Management, 27, 23.
Mahmudah, R. S., Putri, D. I., Abdullah, A. G., Shafii, M. A., Hakim, D. L., & Setiadipura, T. (2024). Developing a Multi-Criteria Decision-Making model for nuclear power plant location selection using Fuzzy Analytic Hierarchy Process and Fuzzy VIKOR methods focused on socio-economic factors. Cleaner Engineering and Technology, 19, 100737.
Martin, D. M., & Smith, D. R. (2025). Comparing SMART and ELECTRE methods for multi-criteria decision analysis: A case study evaluating conservation strategies. Environmental and Sustainability Indicators, 27, 100764.
Masudin, I., Zuliana, P. E., Utama, D. M., & Restuputri, D. P. (2024). Assessment and risk mitigation on halal meat supply chain using fuzzy best-worst method (BWM) and risk mitigation number (RMN). Journal of Islamic Marketing, 15, 842-865.
Mendel, J. M. (2017). Uncertain rule-based fuzzy systems. Introduction and new directions, 684.
Mohaghar, A., Sahebi, I. G., & Arab, A. (2017). Appraisal of humanitarian supply chain risks using best-worst method. International Journal of Social, Behavioral, Educational, Economic, Business and Industrial Engineering, 11, 309-314.
Mutlu, M., Cetin, N. C., & Onder, S. (2024). A novel risk assessment approach for open-cast coal mines using hybrid MCDM models with interval type-2 fuzzy sets: a case study in Türkiye. Systems, 12, 267.
Naz, S., ul Hassan, M. M., Mehmood, A., Espitia, G. P., & Butt, S. A. (2024). Enhancing industrial robot selection through a hybrid novel approach: integrating CRITIC-VIKOR method with probabilistic uncertain linguistic q-rung orthopair fuzzy. Artificial Intelligence Review, 58, 59.
Nguyen, T., Hallo, L., & Gunawan, I. (2024). Investigating risk of public–private partnerships (PPPs) for smart transportation infrastructure project development. Built Environment Project and Asset Management, 14, 74-91.
Peng, H. G., Shen, K. W., He, S. S., Zhang, H. Y., & Wang, J. Q. (2019). Investment risk evaluation for new energy resources: An integrated decision support model based on regret theory and ELECTRE III. Energy Conversion and Management, 183, 332-348.
Rezaei, J. (2016). Best-worst multi-criteria decision-making method: Some properties and a linear model. Omega, 64, 126-130.
Safari, H., Faraji, Z., & Majidian, S. (2016). Identifying and evaluating enterprise architecture risks using FMEA and fuzzy VIKOR. Journal of Intelligent Manufacturing, 27, 475-486.
Sarwar, M., Gulzar, W., & Ashraf, S. (2023). Improved risk assessment model based on rough integrated clouds and ELECTRE-II method: an application to intelligent manufacturing process. Granular Computing, 8, 1533-1560.
Seikh, M. R., & Dey, A. (2025). Triangular divergence-based VIKOR method applied in a q-Rung orthopair fuzzy setting for health insurance plan selection. Journal of fuzzy extension and applications, 6, 300-317.
Wang, L., Zhang, H. Y., Wang, J. Q., & Li, L. (2018). Picture fuzzy normalized projection-based VIKOR method for the risk evaluation of construction project. Applied Soft Computing, 64, 216-226.
Xu, D., Hu, L., Peng, Y., & Jiang, L. (2026). An extended VIKOR method based on multi-valued neutrosophic sets. International Journal of Fuzzy Systems, 28, 1001-1013.
Yu, X., Zhang, S., Liao, X., & Qi, X. (2018). ELECTRE methods in prioritized MCDM environment. Information Sciences, 424, 301-316.
Zadeh, L. A. (1965). Fuzzy sets. Information and control, 8, 338-353.
Zadeh, L. A. (1975). The concept of a linguistic variable and its application to approximate reasoning—I. Information sciences, 8, 199-249.
Zandi, A., & Roghanian, E. (2013). Extension of Fuzzy ELECTRE based on VIKOR method. Computers & Industrial Engineering, 66, 258-263.